We offer initial electrical material quantity take-off by using quantity take off software for procurement purposes from design drawings & preparation of detailed material lists (section wise) from detailed drawings.
Our electrical takeoff service can be used in :-
 |
Wire harness assembly for cost cutting measures and supplier |
 |
 |
Site estimation |
 |
Approved building layout |
 |
Electrical wiring schedule |
| |
|
click here to view sample |
Our electrical takeoffs service consist of eight basic sections: lighting, distribution, devices, branch circuits, equipment circuits, feeder circuits, site work, and special systems.
Electrical Takeoff Procedure :-
Lighting -
As per the lighting fixture schedule count light fixtures by type,. fixture takeoff assemblies will contain lamps and mounting hardware.
Distribution -
Catalog switchboards by size (amperage), voltage, type, and number of sections. List panelboards by size (amperage), voltage, and type. List transformers by size (KVA), voltage (primary and secondary), enclosure rating, and type. List MCCs by size (amperage), voltage, type, and number of sections. Distribution takeoff will comprise all wire terminations, mounting hardware, and accessories.
Devices -
Add up devices by size, type, rating, and location (indoor/outdoor). This takes account of boxes, plates or covers, and fastening hardware.
Feeders -
List feeder circuits by size and type, wire fill, and length. Feeder circuit takeoff will consist of field bends, fittings, pull boxes, and supports. Moreover, feeder takeoff should list any core drill, wall/floor penetrations, sleeves, or fire stopping.
Equipment circuits -
List equipment circuits by size and type, wire fill, and length. Equipment circuit takeoff should comprise fittings, pull boxes, flex whips, and supports. In addition, equipment circuit takeoff will include any disconnects, motor starters, or control stations.
Branch circuits -
List branch circuits by size and type, wire fill, and length. Branch circuits are most often tallied by length and count, such as 350/12. Total length equals 350 feet with 12 segments (a segment has a connection on each end). Branch-circuit takeoff should include supports and any required junction boxes.
Site work -
List circuits by size and type, wire or cable fill, and length. List excavation and backfill by trench section and length, and concrete by cubic yard. List transformer pads, manholes, and handholes by size and type. Site work takeoff should include concrete reinforcing as required, grounding, and utility-specific requirements, such as special raceways and risers.
Special systems -
List control panels and special equipment by system, size, and function. Count special system devices by size, type, and function. List special system circuits by size and type, wire or cable fill, and length. Special systems takeoff should include panel terminations, device boxes, mounting and supporting hardware, and ancillary items shown on the system riser diagrams. |